Project:Column House, Shrewsbury
Project type: New Build
Client: Turner Peachey Chartered Accountants
Value: £680,000
Programme: 6 months
For this project, the company undertook a full project design and management service for the client which included the demolition of an original 1960s library structure, followed by the complete internal refurbishment of the existing three storey building. The project also involved the design and construction of a two storey extension at the rear of the property to provide open plan office accommodation.
The property is located in the Conservation Area of Shrewsbury and therefore sensitive design was paramount in order to bring this project through to fruition.
The scheme included the complete refurbishment of the building including finishes, electrical installations, heating and IT.
Project:Coronation Club, Black Heath, Birmingham
Project type: New Build
Client:
Value: £1.3 million
Programme: 30 Weeks
We were engaged by the Coronation Club following a compulsory purchase order on their existing building to negotiate the compensation for their original club premises and subsequently acquire a new site and carry out a full design and project co-ordination service for the construction of their new facility
Project:Wellington Road Surgery, Newport, Shropshire
Project type: New Build
Client: Wellington Road Surgery
Value: £600,000
Programme: 12 Months
We were engaged to create additional consulting rooms, together with ancillary accommodation including chiropody, conference facilities and additional patient waiting areas. The scheme involved improvements in disabled access which included for the installation of a passenger lift and the improvement of endoscopy facilities, including the creation of improved sterilisation facilities, refurbishment of treatment rooms, together with improvements in nurse care facilities.
Project:Cressage Medical Practice
Project type: New Build
Client: Much Wenlock & Cressage Medical Practice
Value: £120,000
Programme: 3 Months
Cressage Medical Practice required the provision of two additional consulting rooms, together with library / teaching facilities to accommodate the Practice’s intentions to provide on site teaching facilities for GP students attached to Keele University.
We were engaged to undertake full project design and management services.
The project was completed to programme and to agreed budget.
Project:Royal Bank of Scotland
Project type: New Build
Client:
Value: £1.2 million
Programme: 40 Weeks
We were engaged by the Royal Bank of Scotland to act as monitoring surveyor for the Bank who were the main funders for this development. Our service included the monitoring of the construction, ensuring compliance with the client’s brief, ensuring that the project was completed within budget and quality.
Project:Gravel Hill, Ludlow
Project type: New Build
Client: Wilkat Developments
Value: £570,000
Programme: 6 Months
We were involved procuring a design and build contract for the client which included the preparation of the brief and appropriate contract documentation. The assessment of alternative contractors’ tenders and ultimately project managed the scheme to practical completion and beyond.
The scheme involves the provision of 5 self contained apartments, mainly located on the first floor, with a large local retail unit to the ground floor. Close liaison with the intended users was paramount in order to ensure that this project was completed on time, to budget and to a standard required by the retail user.
Project:Unit 10 Sinfin Shopping Centre, Derby
Project type: New Build
Client: Asda Stores Ltd
Value: £80,000
Programme: 4 Months
We were engaged by Asda stores Ltd to carry out the design and project management of the sub-division of an existing shop unit into 3 No. smaller units. Services included the obtaining of all statutory consents, obtaining tenders and managing the project through to completion.
Project:Sixth Form Dormitories, Ellesmere College
Project type: New Build
Client: Ellesmere College
Value: £980,000
Programme:
Project Design & Management of a 20 bed dormitory extension to the 6th form school, together with study and recreational facilities. Services included the obtaining of all statutory consents, obtaining tenders and managing the project through to completion.
Project:Battlefield, Shrewsbury
Project type: New Build
Client: Hallco 746 Ltd
Value: £1,200,000
Programme: 23 Weeks
Construction of 20,000 sq.ft. warehouse facility which will be used for storage purposes. Currently under construction with a projected 23 week construction phase.